Schedules in Niagara 4: weekly schedules, special events and shared holiday calendars

Time control in Niagara 4: boolean, numeric and enum schedules, special events, shared holiday calendars, default outputs and master schedules from a supervisor.

By Berk · 16 November 2026 · 3 min read

Schedules decide when plant runs. On a lot of sites, they’re also where most of the wasted energy is hiding. Niagara 4’s scheduling is flexible, so it’s worth setting up in a way that operators can understand and maintain.

Types of schedule

Schedules come from the schedule palette:

  • BooleanSchedule gives on/off output. This is the usual one for occupancy and plant enables.
  • NumericSchedule gives a number, such as a setpoint that changes through the day.
  • EnumSchedule gives a mode, such as occupied, unoccupied or standby.
  • StringSchedule gives text. It’s rarely used.
  • CalendarSchedule gives a list of dates, such as bank holidays and shutdown days, for other schedules to refer to.
  • TriggerSchedule fires an action at set times rather than holding a value, which suits things like a weekly pump changeover.

Weekly schedule and default output

Each schedule has a weekly schedule, with time blocks for each day of the week and the output value for each block. Outside those blocks, the schedule outputs its default output.

Set the default output deliberately. For an occupancy schedule it should normally be “unoccupied” or “off”. A default of null passes nothing on, and the linked point then falls back to whatever its own fallback is. Sometimes that’s intended; often it’s a surprise.

Special events

Special events override the weekly schedule on particular days. You can define them as:

  • a single date
  • a date range, for example over Christmas
  • a week and day rule, such as the last Monday in May
  • a custom rule
  • a reference to a calendar schedule

When several special events apply to the same day, their order in the list decides which wins. Put the most specific ones at the top.

Share holidays with a calendar schedule

Don’t type the bank holidays into every schedule. Create one CalendarSchedule containing the site’s holidays and shutdown days, then add a reference special event in each schedule that points to it. Next year, update one calendar and every schedule follows.

Linking a schedule to plant

Link the schedule’s out to where it’s needed, for example an enable input in the AHU logic, or a priority input on a writable point. Keep in mind the priority array: if a schedule writes at a low priority and an operator override sits at level 8, the override wins until it’s released or times out.

It often helps to put a small piece of logic between the schedule and the plant, such as optimum start, an extend-occupancy button, or a holiday override. Then the schedule describes when the building is occupied and the logic decides when plant actually runs. See boiler sequencing and optimum start.

Master schedules from a supervisor

On a multi-JACE site, the client usually wants to change “the office hours” in one place. Niagara supports this through the Niagara network:

  • create the master schedule on the supervisor
  • export it to each JACE that needs it, or have the JACEs import it
  • each JACE keeps a local copy that stays in sync with the master

The JACE still runs from its local copy, so plant keeps to time even if the network to the supervisor drops. See the Web Supervisor and the Niagara network.

BACnet schedules

If the controllers have their own BACnet schedule objects, Niagara can read and edit those through the device’s schedules extension, or push Niagara schedules down to them. That keeps time control inside the controller, which is good for resilience. See setting up the BACnet driver.

Making schedules easy to live with

  • Name them by what they control. “Ground Floor Offices Occupancy” means something. “BooleanSchedule3” doesn’t.
  • Keep the number down. Group areas with the same hours under one schedule.
  • Put them where operators can find them, on graphics or in a schedules section of the hierarchy.
  • Check the time zone and daylight saving on every host, so plant doesn’t start an hour early twice a year.
  • Review them with the client at least once a year. Occupancy patterns change, and schedules rarely keep up. See 12 BMS energy savings that actually work.